Project: Leachate Pond at Wyndham RDF

Client: Wyndham City Council

Reconstruction of the existing Leachate Pond located at Wyndham Refuse Disposal Facility. Working next to live tipping site extra care was taken regarding access to reconstruct Wingham’s leachate pond, works including clearing vegetation and remaining sediments from previous ponds including removal of existing structure within the footprint of the pond. Bulk excavation works to formation/subgrade levels. Installation of gas relief trenches, construction of fill embankment around perimeter of the pond, construction of compacted clay liner and anchor trenches. Installation of HDPE and permanent ballast, safety rope and cover soil above embankments